Lifts, a new bridge and a walkway have been installed as improvement works continue at Biggleswade Railway Station.
Network Rail provided an update on the progress of works in a letter to neighbours, which was published by Biggleswade Town Council.


The works, which are designed to provide step-free access from the station entrance to all platforms, are due to conclude in February 2026.
In the letter the rail company writes: "To complete our work, there will be an increase in site activity over the coming months, as we will be removing the temporary access bridge using a crane during weekend night shifts, while platform works will also be taking place."
In the New Year work to demobilise the temporary compound adjacent to the station will begin.
Working hours remain as between 7am and 6pm from Monday to Sunday, and between 9pm and 9am on Saturday nights into Sunday mornings.
Network Rail says there may be a requirement for midweek night work between 10pm and 6am from Mondays to Thursdays, but that they will try and keep it to an ‘absolute minimum.’
There is expected to be an increase in site activity between 9pm on November 22 and 5am on November 24, and from 6pm on December 24 until 6pm on December 26, while the temporary access bridge is removed and the platform is prepared for passengers.
The rail company added in its letter that "delivering major improvement work while keeping the station open is a complex operation which will require a mixture of both day shift and night shift activity."